Thickening claims
|
At its simplest, thickening is a contribution to a claimant’s increased overheads resulting from a client-culpable delay. Thickening is a legal term used in claims when claimants are legally entitled to claim extra costs – over and above the direct costs they may be already claiming – as a result of a delay which is outside their control.
For example, where an extension of time is granted to a contractor, they may also be entitled to claim for time-related costs for the delay period, in other words, in addition to the claim for direct costs, they may also be able to claim for ‘thickened’ overheads resulting from client/employer culpable delay or disruption.
In thickening claims, the claimant must, for example, prove that their head-office overheads had ‘thickened’, i.e. had increased, as a result of the defendant’s breach.
A celebrated case of thickening from October 2016 was that between contractor Flour, which had been engaged to construct an offshore wind farm, and steel fabricator ZPMC. Cracking had occurred in the welding of the steel monopoles and the transition pieces of the turbines for which the court held ZPMC to be in breach of contract. Damages of £15m and €7m were awarded to Fluor as part of direct costs caused by the breach and included costs of additional project management staff, consultants’ costs for the remedial works and costs for extra plant and equipment, as well as for providing extra storage space.
However, in addition, Fluor also claimed for ‘thickening’ costs amounting to 4% of the award – comprising overheads to reflect the increased head-office costs that were necessitated as a result of dealing with the breach of contract. Fluor argued that the thickening costs were just as much a result of the breach as were the direct costs.
The landmark case introduced the concept that certain overhead costs can be linked to a breach of duty just as if they were ordinary losses, i.e. direct losses that include items such as new materials, extra labour and consultant costs necessitated by the breach.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Adversarial behaviour in the UK construction industry.
- Alternative dispute resolution.
- Arbitration.
- Causes of construction disputes.
- Civil procedure rules.
- Conflict avoidance.
- Contract sum.
- Contractual right.
- Construction contract.
- Dispute resolution.
- Dispute resolution boards.
- Disruption claims in construction.
- Expert witness.
- Extension of time.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- How to prepare a claim for an extension of time.
- Litigation.
- Liquidated damages.
- Loss and expense.
- Mediation.
- Modifying clauses in standard forms of contract.
- Notice.
- Preliminaries.
- Scheme for Construction Contracts.
- Variation.
- What is a default?
Featured articles and news
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
























